Case study

Location: City of London

Client: Withers LLP

Main contractor: ISG

Consultant: TB&A

Contract value: £2.3M

Programme: 8 months

20 Old Bailey

Brief

Cat A and high-end Cat B fast-track fit-out for a worldwide solicitor firm in the City of London.

Scope of services

  • Installation of new MER/SER rooms to include UPS.
  • New small power installation from existing Cat A fitout to include wall power, floor boxes, and tea points.
  • Power installation for a new commercial kitchen.
  • Installation of leak detection system.
  • Extension of the BMS network to pick up newly installed fan coils and AC equipment.
  • Installation of a new AHU in the ground floor demise.
  • Reconfigured lighting to suit new layout and installation of specialist luminaires. This was then programmed onto the existing Prolojik lighting system.

Get in touch with Gloster MEP.

Call: 0207 089 6910
Email: enquiries@glostermep.co.uk