Case study
Location: 95 Queen Victoria Street, London
Client: CapGemini
Main contractor: OD Projects
Contract value: £10 Million
Programme: 34 Weeks
Sqft: 90,000
Design: GMEP Design & Build
H&S Scoring: 97.34%
CapGemini
Brief
Project Ruby consists of full Cat B, Commercial office fit-out of Lower ground, Ground, 1st – 4th floors and roof space with the base build being completed by Gloster MEP. Strip out works on level 3 to retain as much material from base build to re-use where possible.
Scope of services
- Plantroom on basement level
- Ventilation, heating & cooling
- Public Health
- Sprinklers & dry risers & Sanitaryware
- BMS engineering controls system
- LV switchgear & distribution supplementary to where needed
- LV Power, Small Power & Mechanical Power
- Lighting, lighting protection
- Low level busbar.
- Fire Alarm, disabled services & secondary containment
- Security & IT Data
Get in touch with Gloster MEP.
Call: 0207 089 6910
Email: enquiries@glostermep.co.uk