Case Study
Material Store
Hub & Fizzy Living
Reidential New Build
Brief
To provide a full M&E install package to a new build development consisting of 23 triplex, 1 duplex and 165no 1-2 bed apartments. This also includes a 4 unit commercial space. Gloster have taken this project from stage E design and specification through to construction with D & B responsibility. There will be green roof spaces on top of all the blocks and a communal green recreational area on level 1 between all the blocks. The build also provides car parking on the ground floor and lower ground basement areas. The Material Store is a part of the old EMI Music site redevelopment in Hayes, Middlesex.
Scope
Electrical and mechanical infrastructure to supply 189 new homes and 4 commercial spaces inc:
- LV Power via a BNO network.
- RWP and SVP public heath services. BCWS services via central tank room.
- Sprinkler and dry riser system.
- Electric Car charging points.
- AOV and Smoke Extract.
- Access control.
- Fire Alarm.
- CCTV.
- BMS.
- Telecommunications networks.
- Satellite and Aerial system.
- LED Lighting Systems
District heating system provided from our onsite plant room via a plate heat exchanger. This is fed underground from the “Power house”, a central site energy centre feeding a number of adjacent buildings which are all part of this development scheme.

Location: Hayes, Middlesex
Client: Paragon Interserve
Contract Value: £7 Million
Programme: 16 Months