Case Study

Material Store

Hub & Fizzy Living

Reidential New Build

Brief

To provide a full M&E install package to a new build development consisting of 23 triplex, 1 duplex and 165no 1-2 bed apartments. This also includes a 4 unit commercial space. Gloster have taken this project from stage E design and specification through to construction with D & B responsibility. There will be green roof spaces on top of all the blocks and a communal green recreational area on level 1 between all the blocks. The build also provides car parking on the ground floor and lower ground basement areas. The Material Store is a part of the old EMI Music site redevelopment in Hayes, Middlesex.

Scope

Electrical and mechanical infrastructure to supply 189 new homes and 4 commercial spaces inc:

  • LV Power via a BNO network.
  • RWP and SVP public heath services. BCWS services via central tank room.
  • Sprinkler and dry riser system.
  • Electric Car charging points.
  • AOV and Smoke Extract.
  • Access control.
  • Fire Alarm.
  • CCTV.
  • BMS.
  • Telecommunications networks.
  • Satellite and Aerial system.
  • LED Lighting Systems

District heating system provided from our onsite plant room via a plate heat exchanger. This is fed underground from the “Power house”, a central site energy centre feeding a number of adjacent buildings which are all part of this development scheme.

Location: Hayes, Middlesex

Client: Paragon Interserve

Contract Value: £7 Million

Programme: 16 Months