Case Study

Apollo & Lunar

Croydon

Fitout of Gvernment Buildings

Brief

CAT A fast track fit-out of 40 floors within a high security building requiring all personnel to be counter terrorism cleared.

Scope of Services

  • Relocation of existing small power
  • New distribution boards to serve new circuits, ensuring compliance
  • Pipework alterations to new tea point areas, requiring pipe freezing due to age
  • Install of new Vivreau hot taps to tea points
  • Power monitoring to both buildings to determine and rectify voltage dips and spikes currently affecting the end user
  • Relocation of reprographics and server rooms to include VRF, DB’s and small power
  • Café and restaurant relocation with new services afforded including pumps to waste due to a technically difficult location

Location: Croydon

Client: Paragon Intserve

Contract Value: £8 Million

Programme: 24 Months

All case studies